::    Construction Updates Mar 12th - 9:24 am

CONSTRUCTION UPDATES

Portland Streetcar Loop Project
Construction Update

For Portland-area construction updates, visit Keep Portland Moving.

For Streetcar construction information, contact please Kay Dannen with Portland Streetcar, Inc.

Construction schedule subject to change.

Construction Map

River District:

Sewer installation on NW 9th & Lovejoy

Weeks of March 1, March 8 & March 15

·      9th Ave will be restricted to 1 northbound lane.

·      2-way traffic will be maintained on Lovejoy.

·      9th Ave will be closed to southbound bicycle traffic.

 

NE Broadway:

Water line installation on Larrabee, Benton & Ross

Week of March 15

·      Up to two lanes on the north or south side of Broadway will be closed during the work hours of 8:30 AM and 6:00 PM.

·      Side streets may be closed on either side of Broadway as the work progresses through the instersections.

·      Bicycle access and accommodations will be made on Broadway.

 

Portland Water Bureau work on N Wheeler from Broadway to Weidler

Weeks of March 1, March 8 & March 15

 

Water line installation from 2nd to Williams

Weeks of March 1 & March 8

·      Up to two lanes on the north or south side of Broadway will be closed during the work hours of 8:30 AM and 6:00 PM.

·      Side streets may be closed on either side of Broadway as the work progresses through the intersections.

·      Bicycle access and accommodations will be made on Broadway.

 

Sewer installation from 2nd to Williams AT NIGHT

Week of March 15

·      Up to two lanes on the north or south side of Broadway will be closed during the work hours of 11:00PM and 7:00AM.

·      Side streets may be closed on either side of Broadway as the work progresses through the intersections.

·      Bicycle access and accommodations will be made on Broadway.

 

Portland Water Bureau work from 2nd to Williams

Week of March 15

 

Water work paving from Grand to 2nd

Week of March 1

·      Work is weather dependant

 

Advanced Utility work at Grand & MLK

Weeks of March 1, March 8 & March 15

 

Portland Water Bureau work at 6th

Week of March 1

 

N/NE Weidler:

Sewer installation from Ross to Williams

Weeks of March 1, March 8, & March 15

·      Up to two lanes on the north or south side of Weidler will be closed during the work hours of 9:00 AM and 6:00 PM.

·      Ross may be closed on either side of Weidler during the work hours of 7:00 AM and 6:00 PM.

·      Williams may be closed on either side of Weidler during the work hours of 7:00 AM and 6:00 PM.

·      Bicycle access will be maintained on Broadway and Weidler with the following detours:

o   Eastbound bike traffic on N Broadway/Weidler, from Benton to Williams, will be re-routed onto the sidewalk from 7AM to 4 PM.  Bikes must yield to pedestrians on the sidewalk. 

o   Westbound bike lane will be closed at times both during the day and night.  Bikes will be detoured at Wheeler, one block north to Dixon and back to Broadway at Benton.

 

Portland Water Bureau work from Williams to 6th

Week of March 15

 

Advanced Utility work at MLK & Grand

Weeks of March 1, March 8 & March 15

Water line installation at 6th

Weeks of March 1 & March 8

·      Up to two lanes on the north or south side of Weidler will be closed during the work hours of 9:00 AM and 6:00 PM.

·      6th may be closed on either side of Weidler during construction.

·      Bicycle access will be maintained on Weidler.

NE MLK:

Portland Water Bureau crew work from Irving to Oregon

Week of March 1, March 8 & March 15

Portland Water Bureau crew work at Davis

Week of March 8

NE Grand:

Advanced Utility work from Hassalo to Clackamas

Week of March 1

 

Track installation from Hassalo to Clackamas

Weeks of March 8 & March 15

·      Up to two lanes on the east side of Grand will be closed during the work hours of 9:00 AM and 6:00 PM.

·      Side streets may be closed east of Grand as the track is installed in the intersection.

 

Track installation from Oregon to Hassalo

Week of March 1

·      Up to two lanes on the east side of Grand will be closed during the work hours of 9:00 AM and 6:00 PM.

·      Side streets may be closed east of Grand as the track is installed in the intersection.

 

Track installation from Burnside to Davis

Weeks of March 1 & March 8

·      Up to two lanes on the east side of Grand will be closed during the work hours of 9:00 AM and 6:00 PM.

·      Side streets may be closed east of Grand as the track is installed in the intersection.

 

NE 7th Ave:

Portland Water Bureau crew work at Multnomah

Week of March 1

E Burnside:

Hydrant relocations from 6th – 12th by Portland Water Bureau Crews (Burnside/Couch Couplet)

Weeks of March 1, March 8

SE MLK:

Sewer installation from Pine to Washington & 3rd to Grand on Oak

Weeks of March 1, March 8 & March 15

·      Oak will be closed during the work hours of 7:00am and 7:00pm

·      Some lane closures on MLK and Grand may occur as work progresses through the intersection.

 

Sewer installation from Washington to Belmont

Weeks of March 1, March 8 & March 15

·      Up to two lanes on the east or west side of MLK will be closed during the work hours of 7:00am and 3:30pm.

·      The two center lanes on SE MLK may be closed to traffic with the two outside lanes being the through lanes.  Some locations will have parking closed to accommodate the work in the center of MLK and ensure it is safe for the crews performing the work.

·      Stark may be closed to one lane during the hours of 9:00 AM to 4:30 PM

 

SE Grand:

Advanced Utility work from Pine to Burnside

Week of March 8

 

Track installation from Pine to Burnside

Week of March 15

·      Up to two lanes on the east side of Grand will be closed during the work hours of 9:00 AM and 6:00 PM.

·      Side streets may be closed east of Grand as the track is installed in the intersection.

 

Water line installation from Madison to Taylor

Week of March 15

·      Up to two lanes on the east or west side of Grand will be closed during the work hours of 9:00 AM and 6:00 PM.

 

Water line installation from Mill to Madison

Weeks of March 1, March 8 & March 15

·      Up to two lanes on the east or west side of Grand will be closed during the work hours of 9:00 AM and 6:00 PM.

·      Bicycle access will be maintained on Hawthorne.

 